Project 07-294
Wilkes-Barre VAMC Boiler Room Load-Carrying Capacity Analysis
Wilkes-Barre, PA
Owner
Wilkes-Barre VAMC
Engineering services to prepare a load-carrying capacity analysis of boiler building roof and floor systems to verify their capacity to support proposed boiler loads.
Results of the analysis were incorporated into a structural narrative that describes existing structural systems, equipment loads, building dead and live loads, design criteria, analysis methodology & identifies deficient structural elements. Existing structural systems and highlighted deficient structural elements were documented on sketches.
Construction Cost: $800,000.00